beautypg.com

Assembling purlin number 4 – Grain Systems Tanks PNEG-4090 User Manual

Page 88

background image

Chapter 7: Roof Assembly

F

1/2 x 1-3/4 in. flange bolt (S-10252)

M

1/2 in. flange nut (S-10253)

G

1/2 in. flange nut (S-10253)

Assembling Purlin Number 4

Purlin number 4 is located forth purlin from the eave.

Before You Begin

Place two roof rafters on the ground with roof panel holes facing up.

NOTE: Temperature cables may also be installed at this location, to determine if temperature cable brack-

ets will be needed, see

About Temperature Cable Brackets and A-Frame Assemblies, page 76

.

What You Should Know

The A-frame roof rafter section consists of two roof rafters identified as the left-hand roof rafter (A) and the
right-hand roof rafter (C).

There are also two different purlin clips, a left purlin clip (E) and a right purlin clip (D). The left purlin clip
has seven holes, compared to the right, which has six holes along the purlin and purlin clip mating surface.

IMPORTANT: Do not drill additional holes in purlin. Install the flange bolts and the flange nuts as dictated

by the number of holes in the purlin.

NOTE: The seventh hole located in the center of the left purlin clip (E) is for identification purposes only.

No hardware is used in this location.

1. Attach a right purlin clip (D) and a left purlin clip (E) to the right-hand roof rafter (C), and install two

flange bolts (F) and two flange nuts (I) into the two top holes.

NOTE: If no X-bracing is being installed, install three flange bolts (F) and three flange nuts (I) in this

step.

2. Attach a right purlin clip (D) and a left purlin clip (E) to the left-hand roof rafter (A), and install two

flange bolts (F) and two flange nuts (I) into the two bottom holes.

NOTE: If no X-bracing is being installed, install three flange bolts (F) and three flange nuts (I) in this

step.

3. Install the purlin (H) to the right purlin clip (D) and the left purlin clip (E) located between each roof

rafter. Install eight flange bolts (B) and eight flange nuts (G), securing the purlin to the purlin clips.

NOTE: If no X-bracing is being installed, proceed to step 8.

4. Attach the bottom X-brace (K) to the right-hand roof rafter (C), and install a flange bolt (F) and a

flange nut (I) into the bottom hole.

IMPORTANT: For adjustment purposes, DO NOT tighten the X-brace flange bolts until all X-braces

have been installed.

5. Attach the top X-brace (J) to the left-hand roof rafter (A), and install a flange bolt (F) and one flange

nut (I) into the top hole.

6. Secure the bottom portion of each X-brace (J and K) with a flange bolt (F) and one flange nut (I).

88

Pneg-4090 90 Ft Diameter 40-Series Bin