PNEG-739 42" - 48" Platforms & Safety Cages

21

48'' Head Service Platform

2

Before attempting any assembly of the platform,
read and follow all directions. Lay out all parts
associated with the assembly. Due to the
assembly of the head service platform, the lower
head assembly may need to be blocked up under
the head and discharge flanges approximately
12" to provide clearance for assembly. Look at
the head assembly to determine the drive side,
which will be the wide side of platform.

First, attach the left and right mainframe
assemblies to the head using 1/2" x 1" hex bolts.

When items with more than one part# are shown you

will only use the one relevant to your service platform.

Example: HSP482xxx single row 48" elevator,

HSP484xxx double row 38"- 42" wide 48" elevator,

HSP485xxx double row 50" wide 48" elevator.

The middle cross member HSP48x106 has a

double hole pattern. Be sure to orientate the

cross members according to Figure 2-1. Right

Drive platform layout shown in all figures.

Mainframe & Cross Member Assembly

FIGURE 2-1

HSP482106 (1) - Cross Member Assembly Double Hole - 26"
HSP484106 (1) - Cross Member Assembly Double Hole - 38"-42"
HSP485106 (1) - Cross Member Assembly Double Hole - 50"

HSP482105 (1) - Cross Member Assembly - 26"
HSP484105 (1) - Cross Member Assembly - 38"-42"
HSP485105 (1) - Cross Member Assembly - 50"

FIGURE 2-1

Then attach the cross members to the mainframe
assemblies with the long end of channels
extending towards the drive side, use the ½" x 1"
hex bolts supplied. (See Figure 2-1)

HSP48402 (1) - Left
Mainframe Assembly

HSP48401 (1) - Right
Mainframe Assembly