Installation, Gold gv water boiler — series 3, Pre-installation planning – Weil-McLain STAR-34 User Manual
Page 4
Part Number 550-110-268/0699
4
GOLD GV Water boiler — Series 3
Installation
Pre-installation planning
1. Follow national, state, local or provincial codes or
regulations when venting GV boiler.
2. Choose vent method from those shown on page 5.
3. Select vent run components from
Table 2
.
Table 3
states maximum vent run lengths and number of
elbows. Do not exceed data in
Table 3
. Longer vent
runs will slightly reduce boiler output. See
Figure 2
.
4. If installing with direct vent method, use same
maximum run length and number of elbows from
Description
Flex-L International, Inc.
Part Number (Note 1)
GV starter tee
--
GV termination coupling
SRAWGVT
45
o
elbow
SRE4503
90
o
elbow
SRE9003
6" pipe
SR06P03
1' pipe
SR12P03
2' pipe
SR24P03
3' pipe
SR36P03
5' pipe
SR60P03
Joiner band
SRJB-14
Weil-McLain Vent/Air Intake Termination Kit
382-200-430 (Note 2)
Weil-McLain Through-Roof or Through-Unused-Chimney Termination Kit
382-200-435 (Note 2)
Notes
1. Flex-L International, Inc. part number. Parts available through Flex-L International, Inc.
2. Weil-McLain part number. Parts available through Weil-McLain distributor.
Table 2
Parts list
step 2. Vent and combustion air connector piping
configurations must match. Use suitable 3" material
for combustion air connector piping, such as:
•
Dryer vent
•
Galvanized steel
•
PVC (3" I.D.)
5. Refer to vent termination
WARNING
, item 19 on
page 3.
Table 3
Vent and combustion air connector piping
lengths and number of elbows
Figure 2
Boiler output
Maximum vent
length (feet)
Total number of elbows
0
2
3
4
5
6
7
8
GV-3 through GV-5 100 80
70
60
50
40
30
20
GV-6
80
60
50
40
30
20
10
--
GV-6
GV-5
GV-4
GV-3
0
20
40
60
80
100
Total equivalent length (feet) of vent
(from boiler to vent termination)
%
Out
put
95
96
98
97
99
100
26800