Test run, Before test run, Execute a test run – Toshiba CARRIER RAV-SP420CT-UL User Manual

Page 28

background image

– 27 –

Under Ceiling Type

Installation Manual

Toshiba

8

TEST RUN

„

Before test run

• Before turning on the circuit breaker, carry out the

following procedure.
1) Using 500V-megger, check 1M

Ω or more exists

between the terminal block L

1

to L

2

and the

ground.
If 1M

Ω or less is detected, do not run the unit. Do

not apply to the remote control circuit.

2) Check the valve of the outdoor unit being opened

fully.

• To protect the compressor at activation time, leave

power-ON for 12 hours or more be for operating.

„

Execute a test run

Using the remote control, operate the unit as usual.
For the procedure of the operation, refer to the
attached Owner’s Manual.
A forced test run can be executed in the following
procedure even if the operation stops by thermo.-OFF.
In order to prevent a serial operation, the forced test
run is released after 60 minutes have passed and
returns to the usual operation.

CAUTION

• Do not use the forced test run for cases other than the

test run because it applies an excessive load to the
devices.

Wired remote control

Procedure

1

Keep

button pushed for 4 seconds or more. [TEST]

is displayed on the display part and the selection of
mode in the test mode is permitted.

Procedure

2

Push

button.

Procedure

3

Using

button, select the operation mode,

[COOL] or [HEAT].
• Do not run the air conditioner in a mode other than

[COOL] or [HEAT].

• The temperature controlling function does not work

during test run.

• The detection of error is performed as usual.

Procedure

4

After the test run, push

button to stop a test

run.
(Display part is same as procedure 1.)

Procedure

5

Push

check button to cancel (release from) the test

run mode.
([TEST] disappears on the display and the status
returns to a normal.)

2, 4

3

1,5

27-EN