Water Reservoir Removal
1. Place the toggle switch in the OFF position and turn
off the water supply to the ice machine at the water
service valve.
2. Disconnect water supply line at float valve quick
disconnect by depressing stainless steel lever.
3. Place the toggle switch in the ICE position. The dump
valve will open and the float reservoir will empty.
4. After the reservoir is empty, place the toggle switch
in the OFF position and disconnect power to the ice
machine at the service disconnect.
5. Remove water float valve coil.
A. Depress coil and rotate 1/4 turn
counterclockwise.
B. With coil wires attached, lift coil off enclosure
tube.
5. QF0800/QC0700 ONLY Rotate quarter turn
fasteners counterclockwise.
6. QF0800/QC0700 ONLY Remove cotter key and pin
from ice chute.
7. Remove top cover from float reservoir.
8. Lift float valve out of float reservoir.
9. Disconnect the drain lines from reservoir.
10. Lift reservoir off of evaporator assembly.
QC700/QF800 Shown
Ice Diverter Removal
QF0400
1. Place the toggle switch in the OFF position, turn off the
water supply and disconnect electrical power to the ice
machine.
2. Remove thumbscrews and lift panel forward.
3. Remove bin level sensor from white plastic panel.
4. Remove ice diverter from bin.
5. When the bin level sensor is reinstalled the correct position
is 4.5” (114 mm) from the left edge of the white panel.
WATER
RESERVOIR
EVAPORATOR
ASSEMBLY
SV2024
3
2
SV2052
LOCATE BIN LEVEL SENSOR 4.5”
FROM EDGE OF WHITE PANEL