Model VSU Make-Up Air

®

®

®

®

®

Start-Up Checklist

Unit Model Number _______________________________

(e.g. VSU-220-H40-UB)

Unit Serial Number _______________________________

(e.g. 04c99999 or 10111000)

Start-Up Date

_______________________________

Start-Up Personnel Name __________________________
Start-Up Company _______________________________
Phone Number

_______________________________

Pre Start-Up Checklist

check boxes as items

are completed.
o Check tightness of all factory wiring connections
o Verify control wiring wire gauge
o Hand-rotate blower to verify free rotation
o Verify supply voltage to the main disconnect
o Verify the supply gas pressure
o Verify remote controls wiring

Start-Up Blower Checklist

refer to Blower

Start-Up section for further detail.

o

Check line voltage

L1-L2 __________

L2-L3 __________

L1-L3 __________

o

Check blower rotation

o

Check for vibration

o

Supply fan RPM

_________ RPM

o

Motor nameplate amps _________ Amps

o

Actual motor amps

_________ Amps

o

Actual CFM delivered

_________ CFM

Optional Accessories

refer to Blower Start-Up

section, Step #6 for further detail.
o

Heating Inlet Air Sensor

________ Actual Setting

Typical setting 60º-70ºF

Start-Up Direct Gas

refer to Direct Gas Start-

Up section for further detail.

o

Check supply gas pressure

________ Maximum

________ Minimum

________ Actual

o

Check Pilot Gas Pressure

________ Actual Setting

Typical 3.0 inch wc

o

Set optional High Gas Pressure Switch

________ Actual Setting

Typical 8.0 inch wc

o

Set optional Low Gas Pressure Switch

________ Actual Setting

Typical 3.0 inch wc

o

Set Burner Pressure Differential

________ Actual Setting

Typical 0.65 inch wc

o

Set the maximum firing rate

________ temp rise

o

Set the minimum firing rate

________ check

o

Set the unit’s operating temperature

________ ºF