1 overview 5-2 inspect the installation, 1 overview, 2 inspect the installation – Innotech Maxim User Manual
Page 44: 2.1 mechanical inspection

MAXIM Installation Instructions
Page 44
© Mass Electronics Pty Ltd 2011
Edition 2.0 dated 20/11/2013
5-1 Overview
The commissioning process of the MAXIM Series controllers can only be performed once the
mechanical and electrical installation has been completed, and is intended to ready the controllers
for full operation. The subsequent sections provide detailed information and steps for the
commissioning process.
5-2 Inspect the Installation
This section of the manual provides detailed steps to perform the final inspection of the installation
process. It is highly recommended that you perform a complete inspection of the mechanical and
electrical installation process to ensure proper operation of the MAXIM Series controllers.
5-2.1 Mechanical Inspection
Please check the following items to complete the mechanical inspection of the installation process:
• Debris such as dust, metal chips, and moisture may have accumulated on the controllers
during the installation process. Please ensure that all controllers are free of any such debris by
thoroughly cleaning as necessary.
• Verify that all controllers are properly installed on DIN rail.
• Verify that cables entering and leaving the cable ducts do not make overly tight bends.
• Verify there is safe access to all MAXIM Series controllers for operation and maintenance.
• Verify that all controllers are installed in a location that is NOT subject to temperature extremes
beyond the normal operating temperature.
• Verify that all controllers are located clear of high current or high voltage cables, and away from
sources that may cause electrical interference.
Customers are encouraged to contact Innotech Control Systems Australia or your nearest authorised distributor for
any clarification or further information regarding the installation process.
NOTE
To prevent injury to personnel and damage to equipment, all electrical power must be turned OFF before starting
the commissioning process. This includes power to the MAXIM Series controllers, and power to the input and
output circuits and equipment. When working with live power ensure that all electrical safety standards for work
on live electrical systems meet local regulatory requirements. Do NOT apply power to any controller or circuit until
instructed to do so by the steps in this section.
CAUTION