beautypg.com

3 outage simulation test – Sanyo SANUPS E11A202U User Manual

Page 24

background image

− 21 −

9.3 Outage Simulation Test

You should perform a test of whether the UPS operates properly during a power outage.
Proper operation is as described below.

Note

Perform this test before powering the connected load devices on.





Note

If your utility power breaker panel is too far away to access conveniently, you can also perform the
test by setting MAIN MCCB to the “OFF” and “ON” positions.
Because the UPS continues inverter operation, there is a small amount of voltage (under 30V) at the
input plug. Do not unplug the plug during operation.

Set the breaker on your utility power breaker panel to “Off”.

Set the breaker on your utility power breaker panel to “On”.

Buzzer

2 beeps..., 2 beeps..., repeated

LEDs

Green INPUT

Blinking

Green INV.ON/STAND BY Lit

Green OUTPUT

Lit

Buzzer

Silent

LEDs

Green INPUT

Lit

Green INV.ON/STAND BY Lit

Green OUTPUT

Lit

Startup UPS for a normal operation. (Please refer to section 9.1.)