beautypg.com

Preparations before operation – Sanyo SANUPS E11A202U User Manual

Page 21

background image

− 18 −

8. Preparations Before Operation

Check the following items before starting operation:

Visually inspect the UPS to verify that there is no visible damage.

Check that the UPS is connected to a utility power source that meets the input

specifications.

Check that the input breaker MAIN MCCB is set to “OFF”.

Check that load devices are connected correctly.

Check that none of the cable connections is loose.
















, ⑤Check input

power source

, ⑤Check load

connections.

Breaker is “OFF”.

This figure shows E11A202U001.

As for E11A202U001J, shape and

the number of receptacles are

different.