Refrigeration Piping

4”

4”

4”

4”

4”

4”

4”

4”

2 sets of pre-charged line sets from

IMI Cornelius

2 extra circuits for stores that install

additional. 2 or 4 barrel machines

Hard pipe from

MCCU to Bohn

evaporators in ice

vault & vault freezer

1 set of pre-

charged lines

furnished by ice

manufacturer

Hard pipe from

MCCU to vault

cooler

Roof Penetrations

All piping and control wiring penetrations are done underneath the fan section of the condensing unit.
Refer to building plans for job details of roof penetration scheme.
The 4” PVC pipe penetrations shown above is a guide for all parties involved.

Head Pressure Controls

Heatcraft does NOT supply headmaster control for the individual display case circuits.
Refer to case manufacturers’ installation instructions for specific provisions needed for head pressure
control.

Note: Heatcraft does include headmaster controls on the ice machine circuit. If the ice machine equipment
from the vendor includes a headmaster already, it will be necessary to clip the pigtail on the headmaster
valve supplied by Heatcraft to disable it from operating and conflicting with the ice machine headmaster.

Figure 11. Piping Connection Layout (MCCU)******

2 sets hard piped

from MCCU to

sandwich cases