6. Removal and Replacement of Water Regulating Valve

(water-cooled model only)

IMPORTANT

Always install a new drier every time the sealed refrigeration system is
opened. Do not replace the drier until after all other repairs or replacement
have been made.

1) Turn off the power supply, remove the panels and close the water supply line shut-off

valve.

2) Recover the refrigerant and store it in an approved container.

3) Disconnect the capillary tube using brazing equipment.

4) Disconnect the flare-connections of the valve.

5) Remove the screws and the valve from the bracket.

6) Install the new valve, and braze the capillary tube.

7) Install the new drier.

8) Check for leaks using nitrogen gas (140 PSIG) and soap bubbles.

9) Connect the flare-connections.

10) Evacuate the system, and charge it with refrigerant. See the nameplate for the required

refrigerant charge and type.

11) Open the water supply line shut-off valve, and turn on the power supply.

12) Check for water leaks.

13) See “IV. 1. Adjustment of Water Regulating Valve.” If necessary, adjust the valve.

14) Replace the panels in their correct position.