6 verifying operation, Power supply and the control circuit, 6verifying operation – Yaskawa 1000 Series Drive Option User Manual
Page 36
36
YASKAWA ELECTRIC TOBP C730600 55D 1000-Series Option PS-A10 Installation Manual
6 Verifying Operation
6
Verifying Operation
After properly wiring and installing the option, use the following procedure to check for
normal operation:
1.
Make sure the unit main circuit power is on, 24 Vdc external power is supplied to the
24 V connector plug, and the 24 V connector plug is connected to the option.
2.
Switch off the main power supply to the unit. The 24 Vdc external power supply
should provide power to the unit control unit.
3.
Check for the red LED on the option indicating proper option operation.
4.
The digital operator on the unit will display “Uv” for about 10 seconds to indicate an
undervoltage condition on the unit.
If “Uv” does not flash on the display screen, check the wiring. If “Uv” fails to appear
on the digital operator after confirming proper wiring, the unit or option may be
damaged.
◆
Power Supply and the Control Circuit
outlines the various conditions under which the option provides power to the control
circuit.
Table 6 Power Supply and Control Circuit
Unit Main Circuit Input
Power Supply
Power from Option
Control Circuit
Operation in Unit
Unit Operation
ON
ON
Normal operation
Possible
ON
OFF
Possible
OFF
ON
Not possible
OFF
OFF
Stop
Not possible