Spohn D03-DFSK1 User Manual
Spohn performance, inc

Spohn Performance, Inc.
494 E Lincoln Ave Myerstown, PA 17067
1-888-365-6064 www.spohn.net
Part# D03-DFSK1 – Dual Front Shock Mounting Kit
2003+ Dodge Ram 4x4 2500 & 3500 | Stock Ride Height
USE OF THIS PRODUCT IS ACCEPTANCE OF SELLER’S DISCLAIMER OF WARRANTY!
By their very nature, competition components are constantly pushed to their limits. While our components are designed to
withstand intense race conditions, it is impossible to control the quality of installation or the varying conditions in which
they are used. It is for this reason that absolutely no warranty or guarantee is either written or implied. Neither the seller
nor the manufacturer will be liable for any loss, damage, or injury – direct or indirect – arising from the use of or inability
to determine the use of any product. Before using, the user should determine the suitability of the product for its intended
use, and the user shall assume all responsibility in connection therewith. Spohn Performance, Inc. makes no guarantee as
to the legality for any specific class. Spohn Performance, Inc. makes no claims, nor does it intend its products to be used
in street driven vehicles. Spohn Performance, Inc. reserves the right to make changes in design or add to or improve on
their product without incurring any obligation to install the same on product previously manufactured. The Buyer agrees to
indemnify and hold Spohn Performance, Inc. harmless from any claim, action or demand arising out of or incident to the
Buyer’s installation or use of products purchased from Spohn Performance, Inc.
INSTRUCTIONS
1. Block the rear tires of the vehicle so that the vehicle is stable and can’t roll. Safely lift the front of the
truck and support the frame with jack stands. Place a jack stand on both the driver's and passenger's
side. Next, remove the front wheels from both sides.
2. Place a pair of hydraulic floor jacks under the front axle. Place one on the driver's side and one on
the passenger's side. Carefully raise up on both jacks at the same time until the jacks come into
contact with the front axle.
3. Open the hood of your truck. Working on the driver's side, locate and remove the upper shock nut.
Also, remove the upper shock retainer washer and grommet. Save the upper shock nut, retainer
washer and grommet. Repeat procedure on the passenger's side.
4. Working on the driver's side, remove the (3) nuts that hold the upper stock shock tower to the stock
location. Save the (3) nuts for later re-installation. Set the upper stock shock tower aside for later re-
installation. Disconnect the front sway bar end link. Repeat procedure on the passenger's side.
5. Working on the driver's side, lower the jack and decompress the shock until the shock and spring
swing clear of the stock upper spring seat (See Photo 5 below). Remove the stock upper spring's
rubber isolator. Remove the stock upper shock mount's lower retainer plate. Repeat procedure on the
passenger's side.
6. Working on the driver's side, install the supplied upper shock mount retainer plate with longer then
stock studs. Place the stock upper spring rubber isolator inside the upper spring seat (make sure it's
clocked correctly). Swing the spring back in place and jack the front axle up to re-seat the spring.
Repeat procedure on the passenger's side.
7. Locate the new driver's side and passenger's side upper dual shock mounting brackets. Also, locate
the stock upper shock tower and the nuts that were removed in Step 4. Working on the driver's side
install the new upper dual shock bracket in between the stock upper coil pocket and the upper shock
tower. Secure using the nuts that were removed in Step 4. Make sure to use Loctite. Torque to 30
ft./lbs. Repeat procedure on the passenger's side. See Photo 1 Below (Driver's Side Shown).
8.
Locate (2) 3/8” x 1.25” long bolts, (2) 3/8” flat washers and (2) 3/8” flanged head lock nuts from the
hardware bag. Working on the driver's side, using the new upper dual shock mounting bracket as a
guide, carefully drill a 3/8” hole into the stock upper coil spring pocket. Secure the new upper dual
shock bracket to the stock upper coil spring bucket using the new 3/8” x 1.25” long bolt and
hardware. Put the flat washer under the bolt head. Make sure to use Loctite. Torque to 30 ft./lbs.
Repeat procedure on the passenger's side. See Photo 1 Below (Driver's Side Shown).