4.8 COMMISSIONING
Please read all installation instructions carefully before proceeding. Wiring diagrams are located
in the appendix. A worksheet for checking off these steps and recording measured values is
located on the following page.
1.
Confirm main unit 
location and adequate 
straight pipe run to 
achieve desired results
Is the main unit located in the correct location as required by the plans?
Is the meter correctly oriented with respect to flow direction?
Compare actual straight pipe upstream and downstream of the main unit location 
to the recommended distances identified in this installation manual. Note: This 
manual is very conservative and assumes the worst-case pipe obstructions; contact 
ONICON’s technical support department to discuss specifics of your application
In order to proceed with the following steps, the System-30 must be operating and connected to the control 
system. There must also be flow in pipes. Flow signal readings should be taken while holding the flow rate 
constant if possible, otherwise, take the various output readings as quickly as possible.
2.
Confirm correct supply 
voltage
Verify that the correct supply voltage is available at the System-30 signal cable 
connections. The System-30 BTU MEASUREMENT SYSTEM operates from 24 V 
AC/DC.
3.
With the HVAC system 
active, verify that the 
diagnostic LED’s for 
FLOW and BTU are 
both flashing.
The LED’s are located on the exterior of the main unit on the end opposite from the 
cables.
The following steps require a multi-meter with the ability to measure DC voltage as well as DC frequency in hertz. 
Remove the six screws that secure the cover to the main unit and carefully lift the cover off.
4.
Check temperature 
readings for T1, T2 
and the differential 
temperature
Set multi-meter for 2 to 4 volt range
T2: (TB2)
Measure DC volts between terminals 2(+) and 3(-)
T3: (TB3)
Measure DC volts between terminals 2(+) and 3(-)
Delta T: (TB2-TB3)
Measure DC volts between terminals 2 and 2
The relationship between voltage and temperature is 10 mV/degree F. 
Multiply the reading in volts by 100 to obtain degrees F.
Compare the calculated temperatures to expected values and to the values shown 
on the network.
5.
Check flow signal
Set multi-meter for DC hertz, voltage range > 15 volts.
The test points for flow are located next to the reset button.
GPM = Frequency in Hz X 60
 
Meter Factor in ppg
(refer to calibration tag for meter factor)
Compare the calculated flow rate to expected values and to the values shown on 
the network.
6.
Check Energy Total 
Output (BTU Output 
Mode 1 and/or Mode 2)
Set multi-meter for ohms
Mode 1:
Measure ohms between terminals 3 and 4
Mode 2:
Measure ohms between terminals 5 and 6
Confirm that the voltage changes state (low to high or high to low) each time the 
controls system register records a new energy total.
End of standard commissioning. Please contact ONICON’s technical service department at (727)447-6140 with 