5

INSTALLATION INSTRUCTIONS

C. AFTER LOCATION HAS BEEN SELECTED:

. Check for obstructions in the area where air condi-

tioner will be installed.

2. The roof must be designed to support 30 pounds

when the RV is in motion. Normally a 200 lb. static

load design will meet this requirement.

It is the responsibility of the installer of this air condi-

tioner system to ensure structural integrity of the RV

roof. Never create a low spot on the roof where water

will collect. Water standing around the air conditioner

may leak into the interior causing damage to the product

and the RV.

3. Check inside the RV for air box obstructions (i.e. door

openings, room dividers, curtains, ceiling fixtures,

etc.)

3. ROOF PREPARATION

Before preparing the ceiling opening, the type of system options must be

decided upon. If a remote sensor is to be used, provision must be made

for it. If the load shed option is to be used, wires must be run from the

load shed control to the Dometic A/C. If a furnace is to be connected,

wires must be run from the furnace to the Dometic A/C. Read all of the

following instructions before beginning the installation.

There may be electrical wiring between the roof and

the ceiling. Disconnect 120 volt AC power cord and the

positive (+) 12 volt DC terminal at the supply battery.

Failure to follow this instruction may create a shock

hazard causing death or severe personal injury.

A. CEILINg OPENINg REQUIREMENTS

. A 4-/4” x 4-/4” (±/8”) opening must be cut

through the roof and ceiling of the RV. This opening

must be located between the roof reinforcing mem-

bers.

2. Mark a 4-/4” x 4-/4” (±/8”) square on the roof

and carefully cut the opening.

3. Using the roof opening as a guide, cut the matching

hole in the ceiling.

B. OPENINg PREPARATION

. If the opening exceeds 4-3/8” x 4-3/8”, it will be

necessary to install spacers.

2. If the opening is less than 4-/8” x 4-/8”, it must

be enlarged.

3. Route a copper 2 AWG, with ground, 20 VAC

supply line from the fuse or circuit breaker box to the

roof opening.

a. This supply line must be located in the front portion

of the 4-/4” (±/8”) opening.

b. The power MUST be on a separate 20 amp time

delay fuse or HACR circuit breaker.

c. Make sure that at least 5” of supply wire extends

into the roof opening. This ensures easy connec-

tion at the junction box.

d. Wiring must comply with all National, State and

Local Wiring Codes.

e. Use a steel sleeve and a grommet or equivalent

methods to protect the wire where it passes into

the opening.

4. The opening created must be framed to provide

adequate support and prevent air from being drawn

from the roof cavity. Lumber 3/4” or more in thickness

must be used. Remember to provide an entrance hole

for power supplies, furnace wiring, 4-conductor con-

trol cable, remote sensing and load shed (Energy

Management System) options as desired.

FIg. 2