Distributor Mounting Instructions

Sheetmetal Duct:

Make a 1-1/4” hole in the duct at desired location. Insert duct

distributor and secure with self tapping sheetmetal screws (sup-

plied by others).

Fiberboard Duct:

Make a 1-1/4” hole in the duct at desired location. Insert duct

distributor and mark the four holes on flange. Drill (4) ¼”- holes

at marked locations. Cut an access hole in duct and install the

enclosed tee nuts from the inside of the duct. Fasten distributor

with enclosed ¼” bolts.

Figure 6

Steam Distribution

Blower Version (6000-1,2)

The 6000 Series Steam Humidifier with the built-in blower pack

should be mounted a minimum of 18” from the ceiling. There

should also be 5 feet of horizontal clearance in front of the unit

to prevent steam from condensing on obstructions (See Figure

1). There is an adjustable louver to adjust the direction of the

steam plume.

WARNING!

Do not adjust this louver to extreme angles as it will re-

strict the airflow causing condensation to form around

the steam distribution manifold.

WARNING!

Locate away from areas where people can walk into the

steam path.

Ducted Version (6000-3,4)

Herrmidifier supplies a stainless steel duct distributor for inject-

ing pure steam into the duct. This can be installed in the bottom

or the side of the duct (See Figure 5). When installing in the side

of the ductwork make sure it is positioned to allow condensate

to drain back down the steam hose. The duct distributor pipe

has a built-in pitch to allow condensate to drain back into the

hose. The hose must be installed with a minimum 8% (1” per

foot) pitch back to the humidifier to allow condensate to drain

back to the steam cylinder (See Figures 5 & 6). A minimum of 5

feet downstream clearance before any bends or obstructions is

recommended for most applications (See Figure 2 ). However,

different psychrometric conditions may require greater or lesser

steam absorption distances. A minimum duct temperature of 60°

F is recommended. Temperatures below this may cause con-

densation to form in the duct. Lined duct may be used if the

thickness is 1” or less.

Figure 5

VERTICAL DUCT

HORIZONTAL DUCT

MIN. 8%

10.00 MIN.

(254 mm)

NO SAGS

ALLOWED

HORIZONTAL DUCT

INCORRECT