Flowserve LR Worthington User Manual
Page 18

LR, LRV, LLR and LR-S USER INSTRUCTIONS ENGLISH 71569088 08-10
Page 18 of 48
flowserve.com
If there is any possibility of the system allowing the 
pump to run against a closed valve or below 
minimum continuous safe flow a protection device 
should be installed to ensure the temperature of the 
liquid does not rise to an unsafe level. 
 
If there are any circumstances in which the system 
can allow the pump to run dry, or start up empty, a 
power monitor should be fitted to stop the pump or 
prevent it from being started. This is particularly 
relevant if the pump is handling a flammable liquid. 
 
If leakage of product from the pump or its associated 
sealing system can cause a hazard it is 
recommended that an appropriate leakage detection 
system is installed. 
 
To prevent excessive surface temperatures at 
bearings it is recommended that temperature or 
vibration monitoring are carried out. See sections 
5.7.4 and 5.7.5. 
 
5 COMMISSIONING, START-UP, 
OPERATION AND SHUTDOWN 
These operations must be carried
out by fully qualified personnel. 
 
5.1 Pre-commissioning procedure
 
5.1.1 Lubrication 
Determine the mode of lubrication of the pump set, 
eg grease, oil, product lubrication etc. 
For oil lubricated pumps, fill the bearing
housing with correct grade of oil to the correct level, ie 
sight glass or
constant level oiler bottle.
When fitted with a constant level oiler, the bearing 
housing should be filled by unscrewing or hinging back 
the transparent bottle and filling the bottle with oil. 
 
Where an adjustable body Denco oiler is fitted this 
should be set to the height shown in the following 
diagram: 
The oil filled bottle should then be refitted so as to 
return it to the upright position. Filling should be 
repeated until oil remains visible within the bottle. 
 
The LR-S pumps are fitted with a different oiler - set 
oil level D as below: 
 
6LR-18S, 10LR-14S and 12LR-14S = 48 mm (1
7
/
8
in.)
8LR-18S, 8LR-23S and 10LR-18S = 53 mm (2
1
/
16
in.)
Approximate oil volumes are shown in section 3.4.2, 
Pump and impeller data. 
 
Grease lubricated pumps and electric motors are 
supplied pre-greased. 
 
Other drivers and gearboxes, if appropriate, should 
be lubricated in accordance with their manuals. 
In the case of product lubricated
bearings the source of product supply should be 
checked against the order. There may be 
requirements for an external clean supply, particular 
supply pressure or the commencement of lubrication 
supply before pump start-up. 
 
33