beautypg.com

Scoreboard mounting, Method 1, Scoreboard mounting -3 – Daktronics BA-515 User Manual

Page 25: Method 1 -3

background image

Mechanical Installation

6-3

would be serious damage to the scoreboard. If you must use this method, ensure a minimum angle
between the chain and scoreboard of at least 45°.

K

Note:

Daktronics assumes no liability for scoreboard damage resulting from incorrect

setup or incorrect lifting methods.


Eyebolts are intended for lifting only. Do not attempt to permanently support the display by the
eyebolts.

In typical multi-section installations, the lower scoreboard section is installed first and secured to the
support beams, and then the upper section is placed atop or above the lower section and attached to the
beams. There may be cables extending from the top of the lower section. Guide these cables into the
hole in the bottom of the upper section for later connection.

If the lift eyebolts are removed, plug the holes with bolts and the rubber sealing washers that were
removed with the eyebolts. Apply silicone or another waterproof sealant to the eyebolt openings.
Inspect the top and sides of the display for any other holes or openings that may allow moisture to
enter the display, and plug and seal those openings as well.

6.3 Scoreboard

Mounting


Use the following table to determine the mounting method for your scoreboard.

Method 1

BA-618, BA-624, BA-918, BA-1018, BA-2003, BA-2004, FB-824, MS-918, SO-
824, SO-918, SO-2008, MS-2002, MS-2004, MS-2011

Method 2

BA-515, BA-518, BA-718, CT-2001, CT-2002, FB-2340, MS-915, TI-218, TI-
418, TI-2003, MS-2006

Method 1
Reference

Drawings:

Display

Mounting......................................................................... Drawing A-44412

Ad Panel Mounting ...................................................................... Drawing A-52187

Installation Specifications, BA 618 .............................................. Drawing A-55006

Installation Specifications, BA 624 .............................................. Drawing A-55007

Installation Specifications, BA-2003 .......................................... Drawing A-158322

Installation Specifications; BA-2004 & BA-2005........................ Drawing A-152777

Installation Specifications, FB-824/SO-824............................... Drawing A-127287

Installation Specifications, MS 918.............................................. Drawing A-55009

Installation Specifications, SO 918.............................................. Drawing A-55010

Installation Specifications, BA 1018 ............................................ Drawing A-61904

Installation Specifications, MS-2002 ......................................... Drawing A-127195

Installation Specifications, MS-2004 ......................................... Drawing A-128788

Installation Specifications, SO-2008.......................................... Drawing A-149074

Installation Specifications; MS-2011 w/TNMC .......................... Drawing A-135414

Drawing A-44412 shows the hardware used for mounting the scoreboard to the beams. Each
section of the scoreboard attaches at the top and the bottom to all the beams. Drawing A-44412
also shows top and side views of the scoreboard secured to the beams. Note that the threaded rods
do not pass through the flanges of the beams, but instead run along both sides of each beam. Refer