13 CB 5-s and CB 5-p Installation Instructions

1.0 FOUNDATION – (see Anchor Bolt Installation Instructions)

2.0 SET THE UNIT

2.1

Screw one set of nuts and washers onto the anchor bolts – After the foundation has set,

screw one set of nuts followed by one set of washers onto the anchor bolts. Set the nuts such

that the lowest washer is about 2½ inches above the concrete at an even height. To accom-

plish this, use a small level and check all three directions. These nuts are not adjustable after

the unit is in place. The bottom edge of the Code Blue unit will be ½-inch above the concrete

when installed.

IMPORTANT: The leveling of the bottom nuts is crucial to the leveling of the unit. A small error

in the adjustment of these will be magnified after installation.

IMPORTANT: A ½-inch air gap is required between the foundation and the unit. Moisture

problems may result if this condition is not complied with.

2.2

Set the Code Blue unit on the anchor bolts – Align the phone plate in the desired direction,

then lift the Code Blue unit over the anchor bolts. Note that the unit weighs 180-220 pounds.

Use appropriate lifting materials and methods to avoid possible injury and/or damage.

2.3

Secure the Code Blue unit – Access the mounting studs through the door on the side of the

unit and tighten the mounting nuts onto the anchor bolts. This may be more convenient if a

long socket, extension and universal joint is used to tighten the hardware.

3.0 INSTALL COMBINATION BEACON/STROBE

3.1

Gasket – Place the strobe gasket on top of the bollard.

3.2

Connect the cords – Plug the wires from the beacon/strobe into the mating plug at the top of

the bollard.

3.3

Fasten the beacon/strobe – Using the supplied screws, fasten the beacon/strobe to the top

of the bollard (If a beacon/strobe guard is being used, it should be installed at this time).

NOTE: The screw threads for the beacon/strobe (and strobe guard) are factory treated to

be water tight. If these screws are removed, they must be retreated before being reinstalled.

4.0 WIRING

4.1

Ground – The ground (green) wire should be stripped and fastened to the supplied grounding

lug.

4.2

24V AC supply – Bring the power connection into the bollard and, using the proper crimping

tool, attach the incoming power wires to the appropriate black and red manifold wires.

4.3

120, 240, 277 & 347V AC supply – Bring the incoming power into the junction box on the

multi-voltage power supply. Using the proper crimping process, attach and fasten each of the

incoming power wires to the appropriate wires in the junction box following the voltage sche-
matic shown on the power supply.

See diagrams next page