Commissioning, Switching on, Operation – Pilz PSS SB TESTER D User Manual
Page 12
Operation
4-2
Operating Manual: PSS SB TESTER
INFORMATION
The battery should not be left in the charger over a long period of time
(several weeks).
• Charge the battery until the LED on the charger flashes (25 % on, 75 %
off)
• Remove the battery and place in the PSS SB TESTER.
Commissioning
Switching on
INFORMATION
Before the PSS SB TESTER is used for the first time, the battery must be
charged for at least 4 hours.
The PSS SB TESTER is switched on via the “ON/OFF” button.
When it is switched on, the unit description “PSS SB TESTER” and its
version is displayed briefly.
The “Start” window then appears. From this window you can access
various menus.
Key to the symbols and function of the buttons in the “Start” window:
: Select test/measurement
: Set transmission rate
F1: Display unit version
F2: Make one of the following settings:
- Set the contrast
- Switch the backlight on/off
- Set the time and date
- Set the signal runtime
- Calibration
F3: Save or delete test results
HLP: Call up help
ESC: Cancel function/close window
VAL: Carry out function