beautypg.com

Pre-start checks – Winco W10PTOS/A User Manual

Page 7

background image

7

3225-00

60706-241

A properly rated and installed double throw manual power isola-

tion transfer switch must be used with a standby generator. The

transfer switch isolates the load from the power line and allows

you to safely operate your loads without endangering the power

line repair crew. See page 6.

The load, connected to the normal terminals of the transfer

switch, is energized by the normal power line when the switch is

in the normal position. The generator, connected to the emer-

gency terminals of the switch, furnishes power when the switch

is in the emergency mode position.

There are two ways to install a manual transfer switch. The first

shown on the left side of page 6 is to install the switch between

the watt-hour meter and the normal distribution panel. As with

any system you must install an entrance rated breaker before the

manual transfer switch. The manual transfer switch must in all

cases be equal to or greater than the rating of the entrance rated

breaker.

The second way to install the system is to purchase and install

an emergency distribution panel and move the circuits you wish

to back up to the new distribution panel. In this case the manual

transfer switch only has to be sized to the amperage of the circuit

breaker in the main distribution panel that is feeding it. See the

right hand drawing on page 6.

Before deciding which system to install, first determine which

loads you can safely run on your PTO generator and the cost

of buying a large manual transfer switch versus the cost of a

smaller switch and the additional distribution panel.

The final item that you are going to have to assemble/wire is the

plug that will be used to connect the generator to the manual

transfer switch. You should have found this load plug in a small

box when you unpacked the PTO generator. If you need addi-

tional plugs for multiple sites you can order additional plugs from

your Winco dealer, the part number is “300137”.

WARNING: Personal Injury

DISCONNECT POWER BEFORE WIRING

IMPORTANT: Use copper wire only. Do not use tinned con-

ductors. Sizing cable - see NEC 400-5.

CORD SIZE: #4/4 conductor cord SO, 1.25 inch dia. max.

To assemble and wire the load disconnect plug, proceed as fol-

lows:

1. Strip outer jacket 2-3/4”.

2. Cut and strip leads to lengths specified for the

particular plug.

3. Disassemble cable clamp and top cover.

4. Remove one blade at a time, insert the stripped end

of the appropriate colored wire designated above,

and tighten the set screw.

5. Fit blades through slots in bottom cover and push

down until home. Please note: Make sure blades

are in correct slots and oriented in accordance with

the diagram above or you will not be able to close

the top cover fully.

6. Place top plastic cover over assembly and partially

tighten the bakelite assembly screw. Realign

blades straight (so they fit into the top bakelite

housing properly) and tighten the assembly screw.

7. Assemble cable clamp over the outer jacket of the

wire and tighten the two clamp screws.

Special Note:

For small size round (less than 3/4”) and flat cables, the

wire clamp may be inverted.

WARNING - Personal Injury:

Failure to wire as instructed may cause personal injury or

damage to device or equipment. To be installed or checked

by an electrician or qualified person only.

PRE-START CHECKS

WARNING: Personal Injury

When working on or around these generators, do not wear

loose fitting clothing or any articles that may get caught in

moving parts.

1. Visually inspect the generator. Check for:

a Correct mounting

b. Physical damage

c. Debris in cooling vents and screens (could

cause generator to overheat).

IMPORTANT

:

The manufacturer recommends that, if the generator has

been stored for any length of time, before using it, the op-

erator remove the control box cover and cooling fan screen,

then inspect the generator for rodent nests or other objects

that could cause generator binding and/or overheating. See

“Cleaning” portion of Maintenance section.

2. Check gear case oil

level. (See Figure 4.)

Case should be filled with

oil to plug marked “OIL

LEVEL.” Fill or remove oil

as required.

NOTE: EITHER TOO LITTLE

OR TOO MUCH OIL CAN HARM

THE EQUIPMENT

See “Lubrication” portion of Main-

tenance for oil specifications.

Page 5

60706-180

0310-00

A properly rated and installed double throw manual power

isolation transfer switch must be used with a standby genera-

tor. The transfer switch isolates the load from the power line

and allows you to safely operate your loads without endanger-

ing the power line repair crew. See page 4.

The load, connected to the normal terminals of the transfer

switch, is energized by the normal power line when the switch

is in the normal position. The generator, connected to the

emergency terminals of the switch, furnishes power when the

switch is in the emergency mode position.

There are two ways to install a manual transfer switch. The

first shown on the left side of page 4 is to install the switch

between the watt-hour meter and the normal distribution panel.

As with any system you must install an entrance rated breaker

before the manual transfer switch. The manual transfer switch

must in all cases be equal to or greater than the rating of the

entrance rated breaker.

The second way to install the system is to purchase and install

an emergency distribution panel and move the circuits you

wish to back up to the new distribution panel. In this case the

manual transfer switch only has to be sized to the amperage of

the circuit breaker in the main distribution panel that is feeding

it. See the right hand drawing on page 4

Before deciding which system to install, first determine which

loads you can safely run on your PTO generator and the cost

of buying a large manual transfer switch versus the cost of a

smaller switch and the additional distribution panel.

The final item that you are going to have to assembly/wire is

the plug that will be used to connect the generator to the

manual transfer switch. You should have found this load plug

in a small box when you unpacked the PTO generator. If you

need additional plugs for multiple sites you can order additional

plugs from your Winco dealer, the part number is “300137”.

WARNING: Personal Injury

DISCONNECT POWER BEFORE WIRING

IMPORTANT: Use copper wire only. Do not use tinned

conductors. Sizing cable - see NEC 400-5.

CORD SIZE: #4/4 conductor cord SO, 1.25 inch dia. max.

Figure 2

To assemble and wire the load disconnect plug, proceed as

follows:

1. Strip outer jacket 2-3/4”.

2. Cut and strip leads to lengths specified for the

particular plug.

3. Disassemble cable clamp and top cover.

4. Remove one blade at a time, insert the stripped end

of the appropriate colored wire designated above,

and tighten the set screw.

5. Fit blades through slots in bottom cover and push

down until home. Please note: Make sure blades

are in correct slots and oriented in accordance with

the diagram above or you will not be able to close

the top cover fully.

6. Place top plastic cover over assembly and partially

tighten the bakelite assembly screw. Realign

blades straight (so they fit into the top bakelite

housing properly) and tighten the assembly screw.

7. Assemble cable clamp over the outer jacket of the

wire and tighten the two clamp screws.

Special Note: For small size round (less than 3/4”) and flat

cables, the wire clamp may be inverted.

WARNING: Failure to wire as instructed may cause

personal injury or damage to device or equipment. To be

installed or checked by an electrician or qualified person

only.

PRE-START CHECKS

WARNING: Personal Injury

When working on or around these generators, do not wear

loose fitting clothing or any articles that may get caught in

moving parts.

1. Visually inspect the generator. Check for:

a Correct mounting

b. Physical damage

c. Debris in cooling vents and screens (could

cause generator to overheat).

IMPORTANT: The manufacturer recommends that, if the gen-

erator has been stored for any length of time, before using it,

the operator remove the control box cover and cooling fan

screen, then inspect the generator for rodent nests or other ob-

jects that could cause generator binding and/or overheating.

See “Cleaning” portion of Maintenance section.

2. Check gear case oil level. (See

Figure 4.) Case should be filled

with oil to plug marked “OIL

LEVEL.” Fill or remove oil as

required.

NOTE: EITHER TOO LITTLE OR

TOO MUCH OIL CAN HARM THE

EQUIPMENT.

See “Lubrication” portion of

Maintenance for oil specifications.