beautypg.com

5 pre-install checklist – NORAC UC5-BC-JD08A User Manual

Page 14

background image



11

5 Pre-Install Checklist

The pre-install checklist is necessary to check the existing sprayer functionality before the
installation.

1. Unfold the sprayer over a flat, unobstructed area (i.e. no power lines…etc.).

2. Ensure all boom-fold operations are functional (place a check mark in boxes below).

3. Bring engine to field-operational RPM and record below.

4. Record the time (seconds) it takes for a full stroke for all boom functions. To ensure

repeatable measurements, take the average of 3 trials.

5. Not all sprayers will have the functions listed below in Figure 4.

Ensure the boom has sufficient travel so it does not contact the ground during

these tests.

Figure 4: Pre-Install Boom Speeds