beautypg.com

5 completing the factoryinstall – NORAC UC4+BC+FT2 User Manual

Page 20

background image

17

4.5 C

OMPLETING THE

F

ACTORY

I

NSTALL

1. Test the functionality of the original

manufacturer’s boom controls. The
NORAC Control Panel (Item E01)
does not need to be powered up for
the original switches to function.

Unfold the booms and raise/lower each

boom and main section. Confirm that
the cabling/hoses are agreeable to the
entire range of motion. If one or more
of these functions do not work, review
the hydraulic and electrical portions of
this manual to check for proper
installation.

2. Cycle all boom hydraulic cylinders fully

from end to end at least 5 times to
remove any remaining air in the
hydraulic system. This includes the
boom roll functions.

3. Unfold the booms and level to 90 cm

(or 35 inch) nozzle height. At this point
ensure the UC4 sensors are reading

from an adequate and uniform target,
such as gravel or dirt, or concrete.

4. For the FT2 system it is recommended

that a full software install be done prior
to delivery of the sprayer. Use the
Install” feature of the UC4+ panel.
(Note – a quick install will not enable
the active roll functionality of the
system).

5. A hydraulic “ReTune” procedure will

be required for optimal performance
once delivered to the end user. This is
required to tune the UC4+ hydraulic
parameters to those of the End-User
tractor hydraulic system.

6. To perform the “Install” procedure,

select the FT2 sprayer type and toggle
YES”. Follow the on-screen
instructions to complete the procedure.