8 completing the installation – NORAC UC4+BC+TA1 User Manual
Page 29
![background image](/manuals/699676/29/background.png)
26
4.8 C
OMPLETING THE
I
NSTALLATION
1. Start up your sprayer and test the sprayer’s
functionality. The NORAC Control Panel
does not need to be powered up for the
original switches to function. Unfold the
booms and raise/lower each boom and main
section.
Confirm that the cabling and hoses
work for the entire range of motion.
2. If any functions do not work, review the
hydraulic and electrical portions of this
manual to check for proper installation.
3. Turn on the power for the UC4+ Control
Panel using the switch on the side of its
chassis.
4. Repeat the Boom Speed Test as described in
Section 4.2 with the UC4+ System installed.
Record the results for comparison in Table
5.
5. For optimal performance, there should be
very little play at the hitch clevis. The
addition of polymer washers can help tighten
up this connection (Figure 31).
Figure 31: Hitch Point
6. The procedure for the installation of the
UC4+ System is now complete. Begin the
AUTOMATIC SYSTEM SETUP procedure as
described in the UC4+ Sprayer Boom
Control Operator’s Manual (M01).