beautypg.com

2 valve mounting – NORAC UC4+BC+JD7 User Manual

Page 22

background image

20

hole and tightened to 35-40 in-lbs to
ensure a tight seal. Reinstall the plug
and tighten to 35-40 in-lbs.

Figure 22: Load Sense Bleed Orifice

Location on Top of Block

4.6.2 Valve Mounting

1. Mount the NORAC valve (V01) on the

sprayer using the valve mounting

bracket (B10).

2. As shown in Figure 23, screw short

side of the threaded rods into the
bottom of the valve block at least 3/8".
The valve mounting holes are drilled and
tapped 3/8 NC-1" deep.

3. Tighten the Hex nuts to hold the rods.

4. Put the mounting bracket on the other

side of the tube and tighten with the
spring washers and the Hex nuts.

5. Cut excess off of the rods, if necessary.

If using bolts, the bolts should

thread into the valve block at

least 3/8". The valve mounting
holes are drilled and tapped 3/8
NC-1" deep. The rule of thumb
for bolt length is 1-1/2" longer
than the tube size.

The recommended location for

the valve is on the angled cross
tube of the parallel linkage on the
sprayer. Orient the valve block
so the "A" and "B" ports face
towards the boom (Figure 24).

You must ensure no hydraulic

components will interfere with

any sprayer parts or be pulled
tight at any time.

Figure 23: Valve Mounting Location

Figure 24: Valve Mounting Example