beautypg.com

8 completing the factoryinstallation – NORAC UC4+BC+HD7 User Manual

Page 32

background image

29

4.8 C

OMPLETING THE

F

ACTORY

I

NSTALLATION

1. Start up your sprayer and test the

sprayer’s functionality. The NORAC
Control Panel does not need to be
powered up for the original switches to
function. Unfold the booms and
raise/lower each boom and main

section.

Confirm that the cabling/ hoses

are agreeable to the entire range
of motion.

2. If any functions do not work, review the

hydraulic and electrical portions of this
manual to check for proper installation.
If you still have trouble, contact
NORAC for assistance.

3. Turn on the power for the UC4+

Control Panel using the switch on the
side of its chassis.

4. Repeat the Boom Speed Test as

described in Section 4.1 with the
NORAC UC4+ Spray Height Control
system installed. Record the results for
comparison in Table 6.

5. The procedure for the installation of the

UC4+ Spray Height Control system is
now complete. Begin the AUTOMATIC
SYSTEM SETUP procedure as described
in the UC4+ Spray Height Control
Operator’s Manual
(M01) using the
HD3 sprayer type.