13. Connect the valve interface cable (C03) to connector S6 on the valve extension cable

(C11).

14. Connect the 2-pin connectors on the valve interface cable to the NORAC valve block, as

shown in Figure 18.

15. The connectors on the valve cable (C03) are marked RIGHT UP, LEFT UP, RIGHT

DOWN and LEFT DOWN. Cables labeled with UP go on the same side as the
hydraulic hoses.

Figure 18: Valve Cable Connections

16. Fasten the 8-way coupler to the boom with cable ties. Connect P6 on C11 to the 8-way

coupler.

17. Connect the boom frame roll sensor to the 8-way coupler.

18. Connect the chassis roll sensor (temp. probe) to the 8-way coupler using cable C01 and a

2-way coupler (E12).

19. Connect two cables (C05) to the 8-way coupler and route along the booms to the wing

sensors. Follow existing cables and hoses to be sure the cable will not be pinched or
stretched.

20. At the sensor brackets, attach a 2-way coupler with terminator (E20) to the sprayer boom.

The 2-way coupler with terminator is the white 2-way coupler. Plug the sensor and the

CANbus cable into the 2-way coupler.

21. Insert the 6-pin plugs (P03) into the remaining connections on the 8-way coupler.

IMPORTANT:

Provide enough slack in all cables to account for the movement of the main