8.2 Valve Block Mounting

Ensure that no hydraulic components will interfere with any sprayer parts or be
pulled tight at any time.

The recommended location for the valve is on the angled cross tube of the

parallel linkage on the sprayer. Orient the valve block so the "A" and "B"
ports face towards the boom (Figure 25).

1. A suitable mounting location for the valve block is illustrated in Figure 25.

2. Insert the threaded rod into the block and use a hex nut to hold the rod. The block holes

are 3/8” NC-1” deep. If bolts are used instead of the threaded rod, ensure the bolts thread
in at least 3/8”.

3. Use the remaining hardware to secure the block to the sprayer.

4. Cut off excess threaded rod, if necessary.