SITE PREP:

1.

Select a site for the tunnel frame that is flat and clear of obstructions. The ground
should be level and free of debris. The area required for a BBTF-55 is 60 ft x 18
ft. The area required for a BBTFD-70 frame is 75 ft x 18 ft.

2.

Layout the ground sleeves as shown in Figure 1. (Note: the BBTF-55 frame is
designed for a 55 ft long net, and the BBTF-70 is designed for a 70 ft long net. If
frame is being installed for a different length net, the overall length of the frame
should be 4 ft longer than the net.)

BBTFSM-55

BBTFSM-70

FIGURE: 1 – FRAME LAYOUT