Fan or Blower System

Start the fan or blower and check for proper rotation.

Check dust pickup points for proper suction. Balance airflow in individual

ducts.

Check for air leakage at all flanged connections.

Equipment Start-Up Sequence

The compressed air supply system must be started first.

When the pressure gauge on the compressed air manifold indicates that

the system is at full pressure (80-90psig) the pulse timer can be

energized.

Dust take away equipment such as rotary airlocks, screw conveyors,

horizontal unloading valves, live bottom bin activators and pneumatic

conveying systems can now be started in their correct sequence.

Check that all access doors, hatches, ports, and other openings are

closed and latched or bolted.

The main exhaust fan can now be started and brought up to speed.

Start the dust-laden air through the collector. The collector should be

started under partial load to allow the cartridges to become slowly and

evenly coated with dust particles.

On pneumatic conveying systems watch the differential pressure gauge

closely for the first hour or so. If unstable, the collector discharge system

may be too small for the volume it is seeing. A quick fix is to reduce the

material feed until the discharge rate can be increased.

Observe the manometer or magnahelic differential pressure gauge

reading. As the new filter cartridges become coated with dust, the

efficiency of the filtering action increases and the differential pressure

across the filter cartridges will also increase. Slowly bring the collector to

full load and note the final pressure drop across the filter cartridges.

Never allow the pressure drop across the filter cartridges to exceed 17”

w.g. maximum or the filter cartridges may collapse.

4-5