The best mounting position for the Cranegard Load Limit Switch is adja-
cent to the wire rope dead end point. It also could be installed adjacent to
the equalizer sheave where wire rope movement is small (a few inches).
The amount of wire rope movement around the equalizer sheave should
be measured by marking the wire rope, noting the amount of movement,
and allowing enough clearance for such movement when mounting the
Cranegard unit.
Section 6 Installation
6-1
Mounting Positions
6-2
Selection
To pick the proper size Cranegard Load Limit Switch for the job, do the
following:
A. Measure the diameter of the rope on which the Cranegard Load Limit
Switch is to be installed.
B. Calculate the maximum load to be applied to the Cranegard Load Limit
Switch, using capacity of the hoist or crane and number of parts of line
to the hook (refer to 2-3).
C. Choose the number of switches and set point.
D. Refer to table 5-1 for proper selection.
Figure 6-A