Before you install, Verifying basic hardware – Cisco SFS 7008P User Manual
Page 3
3
Cisco SFS 7008P InfiniBand Server Switch Installation and Configuration Note
78-17434-01 Rev. A0
Before You Install
•
Three people to complete the installation (highly recommended). The Cisco SFS 7008P switch
chassis weighs up to 106 pounds fully loaded.
Before You Install
Before you begin the installation, do the following:
•
Make sure that you have the right cables and sufficient ventilation.
•
Open the Cisco SFS 7008P package and remove the chassis, rack brackets, parts bag, and
documentation from the box. Remove the packaging from around the chassis. After you have
removed the straps, lift the box up and away from the switch and pallet. Do not cut the packaging,
as you could damage the switch. Save the box and packaging.
•
Prepare a management workstation, such as a PC or laptop running a terminal program with a
rollover M/F DB-9 serial cable (included).
Verifying Basic Hardware
If you have not purchased a fully loaded chassis with high-availability components installed, verify that
you have the minimum components necessary to run the chassis. Specific components in the Cisco SFS
7008P switch (see
and
) have interdependencies on other components.
Check for basic hardware by following these steps:
Step 1
Verify that you have at least one management interface module installed in slot 15 at the back of the unit.
(See
.) Slot 15 is paired with the Fabric Controller in slot 11. (See
.)