INSTALL GROUND FLOOR FRAMES
Use the adjustment bolt
to adjust the elevation
of the frame
Install the first frame by lifting the frame over starter sill and lower the frame down and rest the anchor
hook on pre-set alum anchor at slab/beam.
Use the adjustment bolt on anchor bracket to adjust the elevation of the frame. Adjust the elevation of
the frame to make sure the frame is level, plumb and at the correct height. After adjustment, freeze
the anchor hook for lateral movement by installing FS-339 #10 by 1/2" hex head screw. Use metal
shims if necessary to maintain the nominal distance between bottom of the mullion and top of the
starter sill. Remove shims after adjustment for slip anchor condition at ground floor.
Install FS-339
to laterally freeze
anchor hook in place