Assembly Instructions for
mounting the attachment tube
to frame on Yield-Pro® Planter
The mounting tube must be mounted as shown for
attachments to work properly.
Refer to Figure 1
Note: The longer 4”x2” tube must be mounted on
the left side of the planter.
1.
The 4”x2” mounting tube (2) must be mount-
ed so that the distance from the end of the
tube is 1” from the end of the cap of the 7”x7”
tube (1) as shown.
2.
Using the attachment mounting holes (3), at-
tach attachment tube to frame using 5/8” x 4
1/32” x 3 3/8” u-bolt (4), 5/8” lock washer, and
5/8” hex nut.
Assembly Instructions for posi-
tioning coulter with opener on
Yield-Pro® Planter
Installing Vantage I: Medium openers use 820-
343C, long openers use 204-034D, and long
openers behind gauge wheel use 820-343C.
Installing Coulters: Medium & long openers use
204-034D, unless located behind gauge wheel.
Openers located behind gauge wheel use 820-
343C. Opener located next to openers behind
gauge wheel will require 204-599S. If pullbar in-
terferes with other openers near gauge wheel,
use offset 204-599S.
Refer to Figure 2
1.
When using Vantage I for off-row fertilizer
placement, align coulter 2” to either side of
center of opener.
Refer to Figure 3
2.
In order to allow enough clearance, coulter
must be 25” from front of opener to center of
coulter shank.
Note: After installing coultlers, use an assis-
tant and check all clearances with attach-
ments as planter is slowly folded and
unfolded.
Figure 1
Location of Mounting Tube
22942
Figure 2
Frame Mount Coulter Set-up
22956
Figure 3
Coulter Clearance