All terminal and intercell connections
should be retorqued at least once every year to
11.3 Newton-meters (100 inch pounds).

NOTE: Design and/or specifications subject to change without

notice. If questions arise, contact your local sales rep-
resentative for clarification.

SECTION 20: CAPACITY TESTING

20.0

Capacity Testing

When a capacity discharge test is desired, it is recommended
that it be performed in accordance with IEEE-1188*, latest revi-
sion.

An equalizing charge, as described in Section 14.2, must be per-
formed within 7 days prior to the capacity test. The batteries
must be returned to float charging immediately after the equal-
ize charge completes.

After the capacity discharge has completed, the batteries can be
recharged in the shortest amount of time by following the equal-
ize charge procedure described in Section 14.2.

*IEEE-1188: Recommended Practice for Maintenance, Testing,
and Replacement of Valve-Regulated Lead-Acid (VRLA)
Batteries for Stationary Applications.