Installation and Operating Manual
Series MNKA-B,
acc. to ASME/ANSI
9250-055-en
Revision 01
TM 5976 MPE/Wm
Page 16
Edition 10/2004
7.8.3 Assembly of slide-in unit
Introduce can insert into the can (containment 
shell). If this is not possible, cool can (containment 
shell) insert to approx. 41 °F (5 °C). 
Place intermediate ring 509/1 in the bearing 
pedestal 330.
Insert the entire unit into the lantern 344.
7.8.4 Perform trial assembly of the plain
bearing pedestal with impeller, 
inner magnet assembly and plain 
bearings 
Without adhesive 
Without O-ring 412/3. 
Install bearing bushes 545/1 and 545/2 and press 
in firmly. 
Push on bearing sleeve 529/1 on the impeller side 
and install this unit in the plain bearing pedestal 
339. Make sure that the cams of the anti-torsion 
insert engage properly in the impeller. 
Push distance ring 504 and bearing sleeve 529/2 
onto the pump shaft. 
Push inner magnet assembly 859 onto the pump 
shaft. 
Permit the anti-torsion cams of the pump-side 
bearing sleeve 529/1 to engage in the grooves of 
the impeller. 
Screw on inner magnet assembly 859 together 
with the bearing sleeve and tighten. 
7.8.5 Checking bearing play Z and
impeller distance X
The distances X, Y and Z are indicated in the works 
certificate. See also drawing in Section 9.1.
X:
Distance behind the impeller
Y:
Distance in front of the impeller
Z:
Axial play of the plain bearings
Press inner magnet assembly towards the 
impeller. 
Measure distance X
1
behind the impeller.
Press impeller towards the motor. 
Measure distance X
2
behind the impeller.
Z = X
1
- X
2
Are the values correct? 
These values must be checked after final assembly. 
 
7.8.6 Final assembly
Dismantle trial assembly for determining the bearing 
play again and perform the final assembly. 
With the O-ring 412/3 
With the distance ring 504 
With 1 drop of adhesive on the shaft thread e.g. 
Loctite 243 from Loctite or an equivalent.
Only one drop of the adhesive is to be applied per 
thread. 
Otherwise the next dismantling operation will be more 
difficult or no longer possible without destroying 
components. 
Install plain bearing pedestal 339 and tighten hex. 
screws 901/5.
Strong axial forces are again produced when 
the completely assembled plain bearing 
pedestal is inserted into the lantern. 
Push the entire slide-in unit with housing (casing) 
gasket 401 into the housing (casing) 100 and 
screw together with hex. screws 901/3.
When tightening the housing screws 901/3, make sure 
that the support bracket of the adapter (with motor 
group 140TC) is in contact. 
For tightening torques, see Section 1.2.
7.9 Tests
The pumps are tested with water at the 
manufacturer's. 
The operating data measured are documented in a 
works certificate.
If, during a test after repairs, discrepancies compared 
with the works certificate are discovered, the following 
people can be called in: 
1)
in-house pump office
2)
The manufacturer ITT Richter 
or its local agent 
The following conveying data can be checked using 
the pump performance curves:
Flow rate 
Head 
Power requirement 
NPSHR 