II. Installation Instructions

Figure 3: Hinge Installation & Assembly, LE Boiler

1.

REMOVE CRATE

A. Remove all fasteners at crate skid.
B. Lift outside container and remove all other inside

protective spacers and bracing. Remove container

containing Safety Relief Valve, Boiler Drain Valve

and Pipe Fittings.

2.

REMOVAL OF BOILER FROM SKID

A. Tilt boiler, "walk" boiler backward, and set rear legs

down on floor. Tilt boiler backward, pull skid

forward and set front legs down on edge of skid.

Install close coupling, tee, and plug in return

coupling, see Step 7 and Figure 1. Point tee toward

permanent return location.

B. Tilt boiler backward and remove skid. Be careful not

to damage Burner and Jacket.

3.

CHANGE HINGE POSITION if necessary.

A. Look at the area where boiler will be installed. If

left side of boiler will be less than 12 inches from a

wall, move hinges to right side of boiler. See B

through I below.

B. Pull 2 halves of Burner Swing Door Interlock apart.

Swing Door Interlock is connected to T-T terminals

on R7184A Control. Lift Honeywell R7184A

Control off of Burner Junction Box, open Burner

Ignition Transformer and disconnect wiring harness

from left side of burner. Find round plastic cover

inside Junction Box and install in hole in left side

of burner.

C. Remove 8 sheet metal screws from jacket. Remove

rear jacket box and bend both sides of Jacket

Wrapper up, see Figure 19.

D. Remove 2 (two) 5/16" - 18 x 3" long hex head cap

screws and flatwashers from right side of door.

Remove 2 hairpin cotter pins and 2 hinge pins from

hinges on left side of door and remove Door

Assembly from boiler. Inspect Front and Rear

Door Insulation Pieces and Combustion Chamber

Liner, see Step 6.

E. Remove 4 hex nuts from bolts that attach hinges and

hinge spacers to left side of Tubesheet. Remove 4

hex head cap screws that attach hinges to door.

F. Attach 2 hinge brackets & spacers to Tubesheet and

2 hinge brackets to Door on right side of boiler. 3

Holes in each Hinge Bracket must line up with 3

matching holes in Spacer, Tubesheet or Door. See

Figure 3. Tighten hex nuts, bolts and screws by

hand only.

G. Replace door assembly. Hinge brackets attached to

door must rest on top of hinge brackets attached to

tubesheet. See Figure 3. Slide hinge pins through

hinges from top and install cotter pins. Close door

and install 5/16" - 18 x 3" long hex head cap screws

through flatwashers and left side of door and into

tapped holes in tubesheet. Tighten all hex nuts,

bolts and screws. When door is installed properly,

it is parallel to Tubesheet when viewed from top

and sides.

H. Bend sides of Jacket Wrapper down and attach 2

Jacket Straps to 4 slots at bottom of Jacket Wrapper

sides with sheet metal screws. Install Rear Jacket

Box with 4 sheet metal screws. See Figure 19.

I. Connect wiring harness to a knockout on right side

of Junction Box and install Honeywell R7184A

Control, see Wiring Diagram, Figures 11A and 11B.

Reconnect Swing Door Interlock.