Installation instructions, Caution, Danger – Autoquip COIL TRANSFER CARS User Manual
Page 14
14
INSTALLATION
1. Make sure installation area is clean before starting.
2. If the permanent electrical work is not complete, some means of temporary lines with
an on-off device for the motor should be set up for testing purposes.
3. Place the lift in the installation area, typically on tracks or rails which are supplied
and installed by the customer or installer.
CAUTION!
When moving the lift, do not attempt to pick it up by the platform; it is
hinged and could be damaged. Pick up the lift from under the base frame
ONLY using a strap sling.
4. Make temporary electrical connections. Raise the lift to the top of its travel and
check for the proper height.
DANGER
!
Do not work under lift without Maintenance Device! To avoid personal
injury, NEVER go under the lift platform until the load is removed and the
scissors mechanism is securely blocked in the open position. See "Lift
Blocking Instructions" section.
5. Run the lift in forward and reverse and check for proper motor rotation and speed.
6. Make permanent electrical connections and operate the lift through a few cycles.
7. Check the oil in the reservoir and add oil, if necessary. See “Routine Maintenance”
section.
8. Clean up any debris from the area. A clean installation makes a good impression
and creates a much safer environment!
INSTALLATION INSTRUCTIONS