4 commissioning, 1 available interfaces, 2 cable installation – ADS-TEC BPC1000 User Manual
Page 14: Ommissioning

Industrial PCs BPC1000
14
© ads-tec GmbH • Raiffeisenstr.14 • 70771 Leinfelden-Echterdingen
4
C
OMMISSIONING
The power supply connection and interfaces of this device are installed at the device front
panel. All supply leads and all required data leads have to be connected before starting
commissioning.
Warning:
The device must be switched off before connecting or disconnecting any cables in order
to prevent damage to the electronics!
The device may only be switched on after acclimatising to the ambient temperature in
order to avoid condensate accumulation. Make sure to meet the permissible voltage
requirements for this device.
After switching off and before switching on you must wait for at least 5 seconds.
Note:
The screen of a data cable must always be connected with the connector housing (EMC).
Under the embedded operating system, interfaces must explicitly be enabled and required
drivers must be installed for being able to use them.
4.1 A
VAILABLE INTERFACES
PC
VERSION
I
NTERBUS VERSION
S
ERCOS VERSION
4.2 C
ABLE INSTALLATION
The BPC 1000 interfaces are installed in the front of the device. Install required data leads
and secure them against slipping out.