Page 6: Smr-ac system mounting
❑ SMR-AC Installation and Setup
52
Addendum - SMR-AC CAFSPro Installation Guide
p/n: 029-0020-78-0
WARNING - continued !
PLACE A BRACE, APPROXIMATELY 3’ (1 METER) BETWEEN THE LIFTING
STRAPS / CHAINS TO PREVENT APPLYING EXCESSIVE PRESSURE TO THE
MANIFOLDS AS THE SYSTEM IS LIFTED INTO PLACE. APPLY A STRAP
AROUND THE FRONT SUCTION INLET AS SHOWN TO DEVELOP A THREE-
POINT LIFT, MAKING SURE THE SYSTEM IS BALANCED. ALSO SEE FIG-
URE A-1: “LIFTING THE SMR-AC SYSTEM (THREE-POINT LIFT).”
Figure A-1: Lifting the SMR-AC System (Three-Point Lift)
A.2
SMR-AC SYSTEM MOUNTING
SMR-AC CAFSPro Main Pump System Assembly
When installing the SMR-AC CAFS System to the apparatus chassis, use
accepted practices for mounting. Review previous Section 3 “Receiving
and Inspection” beginning on page 13. Also see Figure A-2: “Shock Mount-
ing” on page 53.