PlACING A REGUlATOR IN SERVICE (Continued)
CHECkING FOR PROPER OPERATION
Refer to the control unit instruction manual and use
the following procedure to check for proper regulator
operation. (Switch designations referenced below are
applicable to the HI/ICMI control.)
1. Set the MOTOR CONTROL AUTO/MANUAL switch to
“MANUAL”.
2. Holding the the MOTOR CONTROL RAISE/LOWER
switch in the “LOWER” position, run the regulator in
the lower direction until the control panel LOW BAND
indicator illuminates.
3. Set the MOTOR CONTROL AUTO/MANUAL switch to
the “AUTO” position. After a time delay, the regulator
will automatically return to an IN-BAND condition. The
control panel IN-BAND indicator will illuminate.
4. Set the MOTOR CONTROL AUTO/MANUAL switch to
the “MANUAL” position.
5. Holding the MOTOR CONTROL RAISE/LOWER switch
in the “RAISE” position, run the regulator in the raise
direction until the control panel HIGH BAND indicator
illuminates.
6. Set the MOTOR CONTROL AUTO/MANUAL switch to
the “AUTO” position, After a time delay, the regulator
will automatically return to an IN-BAND condition. The
control panel IN-BAND indicator will illuminate.