6. Commissioning, operation
GB
Pressure and leage test
Every device is subjected to a pressure examination in the work. If in the plant still a
strength examination (system pressure examination) be required, pressure may not
exceed the examining pressure means 1.5 times the indicated pressure on the type plate
and the flange.
CAUTION!
For all examinations and uses, in principle, these are indicated on the type
plate authoritatively!
6.2.2 Switching amplifier model LSO.25 (in makrolon housing)
■
Prepare mounting holes (see figure below)
■
Detach the clear cover from the housing
■
Insert mounting screws from cover side into the mounting holes
■
Tighten the mounting screws
6.3 Electrical connection
WARNING!
For the electrical connection, comply with all relevant regulations.
The transducer and switching amplifier connections are both marked with the colors WS
(white) respective 2d, BR (brown) respective 4d and GN (green) respective 6d. Connect
them according to the connection plan.
mounting