Assemble the frame

1. Support the frame assembly in a horizontal position.
2. Check the shaft-end play by moving the shaft forward and backward by hand, and note any indicator

movement.
If the total indicator reading is greater than the values in this table, then disassemble the shaft and
determine the cause.
Use this table as a reference for shaft-end play values.

Table 14: Shaft-end play

Frame

Double row bearing

Duplex bearing

STi inches (millimeters)

0.0011 (0.028)
0.0019 (0.048)

0.0007 (0.018)
0.0010 (0.025)

MTi inches (millimeters)

0.0013 (0.033)
0.0021 (0.053)

0.0009 (0.023)
0.0012 (0.030)

LTi inches (millimeters)

Not applicable

0.0010 (0.025)
0.0015 (0.038)

XLT-i inches (millimeters)

0.0014 (0.036)
0.0023 (0.058)

0.0010 (0.025)
0.0015 (0.038)

SCALE

0.160

3. Check the shaft-sleeve (126) runout.

Maintenance