Hawkeye Series 5000 EPRV User Manual
Series 5000 eprv
This document contains the operating instructions and recommended procedures for installing a Hawkeye Industries Series 5000 Emer-
gency Pressure Relief Vent.
Requirements
Ensure that the tank has been fitted with a man way opening and
the appropriate flange connection.
Tools
Parts Required
Unladen Weights
A.) Installing the Series 5000 EPRV
Lift the EPRV onto the tank using lifting lugs and proper lifting procedures.
Do not lift device by hand or with any weight plates installed.
Clean all debris and residue from flange gasket and mating surfaces. Set
flange gasket on the tank flange and EPRV on the flange gasket, aligning
the bolt patterns.
Installation & Maintenance Guide
Series 5000 EPRV
QTY
Part
Installation
►
1
Series 5000 EPRV, c/w
►
1
Flange Gasket
► varies Mounting Hardware
► varies Dead Weight set pressure plates
Maintenance
►
1
Replacement Gasket
►
Dow Corning #4 Electrical Insul. Compound (or eq.)
QTY
Tool
All Models
►
1
Side Cutters
►
2
3/4” Open End Box Wrench
►
1
3/4: Deep Socket, 1/2” Max Drive
►
1
Torque Wrench from 59 to 121 ft-lb
For 20” and 24” API 650 Flange Mount EPRVs
►
2
15/16” Open End Box Wrench
►
1
15/16” Socket
For 20” ANSI 150# Flange Mount EPRVs
►
1
1-11/16” Open End Box Wrench
►
1
1-11/16” Socket
For 24” ANSI 150 Flange Mount EPRVs
►
1
1-7/8” Open End Box Wrench
►
1
1-7/8” Socket
Series 5000 EPRV Installation Instructions, May 2014
1
Contents
A.) Installing the Series 5000 EPRV
B.) Series 5000 EPRV Operating Instruction
C.) Maintenance
►
SIZE
W/ STEEL BASE
W/ ALUMINUM BASE
20 API
143 lb [64.7 kg]
111 lb [50.2 kg]
20 ANSI
144 lb [65.2 kg]
112 lb [50.7 kg]
24 API
187 lb [84.6 kg]
149 lb [67.4 kg]
24 ANSI
192 lb [86.9 kg]
153 lb [69.2 kg]
1
2