C.) Gauge Board & Indicator Kit with Magnetic Clips
D.) Required Number of Magnetic Clips
Note the order of the gauge boards by the de-
cals and connect each piece together using the
supplied splices and the 1/4 in. X 3/4 in. ma-
chine screws, nuts, and washers.
Omit the nuts and washers on the top pair of
bolts of the lower gauge board, and fasten di-
rectly to the magnetic gauge board clips.
At the midpoint of each gauge board section,
drill two 17/64 (or 9/32) holes, 3” apart sym-
metric about the long axis of the board.
Use the supplied template below.
►
►
►
►
DRILL
17/64 OR 9/32
THROUGH
2 PLACES 3.00
AP
AR
T
DRILL
TEMPLA
TE
ALIGN TO
EDGE OF
GAUGE BOARD
8 Ft Gauge Board (1x 8ft section) - 3 magnetic clips required
10 Ft Gauge Board (1x 10ft section) - 3 magnetic clips required
16 Ft Gauge Board (2x 8ft sections) - 5 magnetic clips required
20 Ft Gauge Board (2x 10ft section) - 5 magnetic clips required
24 Ft Gauge Board (3x 8ft section) - 7 magnetic clips required
32 Ft Gauge Board (4x 8ft section) - 9 magnetic clips required
Secure the top bracket with the indicator cable
pulley to the existing holes, 0.75 in. from the
top of the gauge board and the corresponding
gauge board clip using the 1/4 in. X 3/4 in. ma-
chine screws, nuts, and washers.
Secure the bottom bracket to the existing
holes, 0.75 in. from the bottom of the gauge
board and corresponding gauge board clip
using the 1/4 in. X 3/4 in. machine screws,
nuts, and washers.
Install the complete gauge board and indicator
assembly on the tank. Align and move as re-
quired to match gauge head.
The following chart outlines the minimum required number of magnetic gauge board clips recom-
mended by Hawkeye. For sizes not listed here, please consult Technical Bulletin TB-1211-GB for
calculating the required number of clips.
1.)
2.)
3.)
4.)
5.)
Installation Complete. Proceed to Float Guide Kit or Gauge Head Installation