Installation

40

900-0144-01-01 Rev A

Functional Test

Once the mounting, wiring, and other installation steps are completed, proceed to the Radian Series
Inverter/Charger Operator’s Manual
. The Operator’s Manual has steps for system commissioning. These

include powering up and performing a functional test on the inverter system, as well as powering

down and adding new devices to an existing system.
Refer to the MATE3 System Display and Controller Owner’s Manual (or the appropriate system display
manual) for programming instructions and menus.

When commissioning a grid-interactive system for use in Australia:

To meet the standard AS4777.3, the acceptance settings shall not exceed the following. The factory

default settings meet these requirements.

Table 5 AS4777.3 Acceptance Settings

Minimum

Voltage

Maximum

Voltage

Minimum

Frequency

Maximum

Frequency

200 Vac

270 Vac

45 Hz

55 Hz

Preventative Maintenance

The Radian inverter requires almost no regular maintenance. However, OutBack recommends the

following items on a periodic basis:

Check all electrical connections periodically for tightness using the torque values from pages 19 through 22.

Check the fan screens on each module and clear them of any debris.