background image

The relay inside the DS-2C acts as a switch. While not as convenient as directly supplying power for the

load this allows you to operate the DS-2C from one voltage while controlling a load of a different voltage

without adding an external relay or contactor. For example, the DS-2C can be powered from 120VAC but

can directly control a 24VAC signal for a boiler system or 277VAC for heating wire. The following diagrams

show some possible wiring schemes for connecting the DS-2C to your load. Your load may be a direct

connection to heat cable, a heater, a contactor coil, or a control voltage. For clarity the green safety

GROUND leads are not shown.

BROWN

BLUE

YELLOW

YELLOW

LOAD

SWITCHED 240VAC

LOAD CENTER

DS−2C

POWER SUPPLY

CB

Recommended Switch Settings by Function

Function

Trigger

LD Off

LD On

LTC

DEL

RAIN SNOW

Snow sensor w\o LTC

TT>AT

2 Min

2 Min

OFF

OFF

OFF

ON

Snow sensor w\LTC

TT>AT>5°F

2 Min

2 Min

ON

OFF

OFF

ON

Snow controller w\o LTC

TT>AT

30-90 Min

2-6 Hr

OFF

ON

OFF

ON

Snow controller w\LTC

TT>AT>5°F 30-90 Min

2-6 Hr

ON

ON

OFF

ON

Precipitation sensor

Not Used

2 Min

2 Min

X

OFF

ON

ON

Precipitation controller

Not Used

30-90 Min

2-6 Hr

X

ON

ON

ON

Rain sensor

AT>TT

2 Min

2 Min

X

OFF

ON

OFF

Rain controller

AT>TT

30-90 Min

2-6 Hr

X

ON

ON

OFF

LT thermostat w\o LTC

TT>AT

2 Min

2 Min

OFF

X

OFF

OFF

LT thermostat w\LTC

TT>AT>5°F

2 Min

2 Min

ON

X

OFF

OFF

X = Do Not Care

Fine Adjustment for Efficient Operation

The DS-2C is shipped with the TRIG TEMP and DELAY OFF adjustments in the center position,

representing 39°F (3.9°C) and 60 minutes of Delay-Off time respectively. It is also set for highest

SENSITIVITY. Depending on local conditions the user may find that fine adjustment of the controls may

provide more satisfactory operation. If the sensor does not trigger during very wet snows the trigger

temperature may need to be adjusted higher. Constant triggers from snow falling from trees or overhangs

may be reduced by adjusting SENSITIVITY. The Delay-Off time can also be adjusted to provide clean

melt-off without excessive running time. Fine adjustment can both save operating expense and provide

more reliable operation. However, to keep reliability high, always make adjustments in small increments.

Use Care When Replacing the Front Cover. Do Not Pinch the Gasket or Overtighten the Screws.

Manual Override Switch Operation

An override switch mounted on the side is provided for testing and special operational requirements.

Placing the switch in the AUTOMATIC position will allow the sensor to operate normally, activating the

controlled equipment as needed. Placing the switch in MANUAL ON will close the load relay, activating the

controlled equipment. The “STANDBY/RESET” position prohibits triggering of the unit, clears any active

delay timer, and opens the load relay. In order to reduce excessive runtime for the heater the “Manual

On” mode will remain in effect for up to 40 hours, then return to “Automatic” mode, even if the

switch is still in the “Manual On” position. However, any trigger of the system will restart the 40

hour “Manual On” timer. You may put the DS-2C back into “Manual On” mode by switching to

AUTOMATIC, then back to MANUAL ON. This will also restart the 40 hour timer.

If the override switch is placed in MANUAL ON for less than 2 seconds, then switched back to

AUTOMATIC the controller will execute one Delay-Off cycle. This can be used to clear a frost, hail, or

drifted snow buildup without the danger of leaving the system in a continuous “Manual On” condition.

“Standby/Reset” can still be used to clear this Delay-Off cycle.

4

Typical Load Wiring

The Yellow load leads are N.O. contacts and do not supply power directly to your load

NEUTRAL BUS BAR

CB

BROWN

BLUE

YELLOW

YELLOW

LOAD

DS−2C

SWITCHED 120VAC

NEUTRAL

LOAD CENTER

POWER SUPPLY

120VAC In, 120VAC Load, Heat Cable or Similar (Also Applies To 277VAC)

240VAC In, 240VAC Load, Heat Cable or Similar

5