3.4 General requirements

INFORMATION!
The following precautions must be taken to ensure reliable installation.

Make sure that there is adequate space to the sides.

Protect the signal converter from direct sunlight and install a sun shade if necessary.

Support the pipeline on both side of the flowmeter.

Do not expose the signal converter to intense vibration. The flowmeters are tested for a
vibration level in accordance with IEC 60068-2-64.

Figure 3-1: Avoid vibrations

Figure 3-2: Avoid strong magnetic fileds

Figure 3-3: Horizontal piperun

CAUTION!
Install in a slightly descending pipe section to prevent air from collecting and to avoid faulty
measurements (meter can drain).