6.0 MAINTENANCE
6.1 MAINTENANCE SCHEDULE
Item
Procedure Frequency
Reference Notes
check lube clean
change hours
9
6
S
5
Wheel Hubs
main frame
6
100
100 hr or annually
re-pack bearings or 2 pumps grease
Metering System
sprockets and chains
6
25
25 hr or every 2 days
use dry graphite lubricant
Metering Components
Seed Hawk
®
100
100 hr, or, before seeding, or,
between product changes
Fan System
intake
9
10
10 hr or daily
remove accumulated debris
Fan System
fan blades
9
10
10 hr or daily
must be intact and clean
Fill Auger System
10 in
100
when changing between products,
or,
when stored for long periods of time
Fill Auger System
pillow block bearings
6
10/100
10 hr or daily, and,
100 hr or annually
Fill Auger System
universal joints
6
10/100
10 hr or daily, and,
100 hr or annually
Tank Return Line
open - drain in pail
9
100
at end of seeding season, or,
when stored for long periods of time
Tires
air pressure
9
10
10 hr or daily
inflate to proper pressure
NOTE: The HEX BORE bearings on each Stainless Steel meter are sealed.