Qualcraft End Rail User Manual
Page 9

Installing Planks and Rails
1. Spread Trus Joist� Scaffold Planks, 2x4 D.F #1 handrails, to
each bracket.
2. Always install first section of planks and rails, from an
extension ladder.
3. From there, complete the entire run of planks and rails from
either the scaffold or a ladder.
Page 7
4. Continue lapping planks in one direction for consistent overlap.
(This simplifies the removal process. )
CARPENTRY INSTRUCTIONS
Before removing the Stacker Bracket� system, complete all roof
carpentry, including the following.
�
Install all roof vents and frieze blocks
�
All hardware required by engineer. (L50, A35, H1, etc.)
�
Complete all fascia
�
Complete all roof sheeting and nailing
�
All roof carpentry
�
Nailing inspection approved and signed off
�
Fireplace stacks, pop-outs, skylights, dormers, etc.
�
Chevrons at gable ends w / OSHA approved harness.
�
Holes cut for heat
�
Tile kick at the eve installed
Page 8
SAFETY NOTE
Do not use a stepladder as a lean-to ladder.